Order of Ops

Task Ideation

Phase 1 - Estimate 50h* - 1 sprint

<aside> 💡

Move to new VM & foundational structure

</aside>

  1. Store Tableau VC SQL Statements in Notion & Update Auth | Tam (Oscar) | 8h
  2. Create & Store VC SQL in DB | Seaver | 3h
    1. Create temp-analytics schema
    2. Create / Update tableau service role for access
    3. Create View
  3. Create New Tableau VC via SQL to temp-analytics | Tam (Oscar) | 16h
  4. Conduct Migration Copy Enhancements via SQL Files | Seaver & Miles | 16h
    1. Copy DB Locally - 1h
    2. Write SQL files - 8h
    3. Validate End State - 2h
    4. Repeat if Needed - TBD
    5. Test service credential “happy path” - 2h
  5. Migrate DB to New HM Linode VM | Seaver | 7h
    1. Initialize new HM VM - 2h
    2. Copy DB - 1h
    3. Apply SQL Batch - 1h
    4. Deploy Sync Program service role updates - 1h
    5. Adjust pg.kostorage.tech - 1h

Phase 2

<aside> 💡

Enhance & optimize existing DB foundational structure

</aside>